    mines been showing "received at licensing section" for a month now

  2. #22
    User
    Join Date
    Apr 2012
    Location
    Cape Town, Brackenfell
    Age
    30
    Posts
    247

    Default Re: steps in process

    Quote Originally Posted by glenn.watson View Post
    mines been showing "received at licensing section" for a month now
    Email a complaint to the following :

    service@saps.gov.za
    complaints.invest@saps.org.za
    ComplaintsNodalPoint@saps.gov.za
    ikinnes@parliament.gov.za
    bmbengo@parliament.gov.za
    Takalani.ramaru@csp.gov.za
    Busi.mazibuko@csp.gov.za
    cfrenquiry@saps.gov.za
    cfr.enquiries2@saps.gov.za

  3. #23

    Default Re: steps in process

    thats a lot of email addresses have you had any success emailing them?

    i don't want to irritate anyone there and get my license rejected

  4. #24
    User
    Join Date
    Apr 2012
    Location
    Cape Town, Brackenfell
    Age
    30
    Posts
    247

    Default Re: steps in process

    Had success with my competency application. Hassled them until it was completed.
    I've also contacted CFR Enquiries and Provincial Enquiries because my application got stuck at provincial for over a month. Since that my application went from provincial - CFR - Licensing within 2 weeks

  5. #25

    Default Re: steps in process

    thanks

  6. #26
    User
    Join Date
    Feb 2017
    Location
    Durbs
    Age
    45
    Posts
    254

    Default Re: steps in process

    I recently saw that there was an internal memo extending the 90 working days to 120 working days. I called in on behalf of a client and the call centre agent informed me that CFR's timeline was now 150 working days due to Covid19 and Amnesty backlogs. This has not been confirmed via internal memo yet.

  7. #27
    User
    Join Date
    May 2012
    Age
    46
    Posts
    13

    Default Re: steps in process

    Good morning
    Regarding an amnesty app, competency approved already, licence in prep for consideration....at which of the mentioned stages could one assume that the licence is approved? Surely if the competency is approved then licence should be granted?

  8. #28
    User
    Join Date
    Aug 2011
    Location
    Sandton
    Posts
    8,838

    Default Re: steps in process

    Quote Originally Posted by jiggajono View Post
    I recently saw that there was an internal memo extending the 90 working days to 120 working days. I called in on behalf of a client and the call centre agent informed me that CFR's timeline was now 150 working days due to Covid19 and Amnesty backlogs. This has not been confirmed via internal memo yet.
    They can make it whatever they like but they'll still fail to meet it on purpose or just through sheer incompetence.

  9. #29
    User
    Join Date
    May 2012
    Age
    46
    Posts
    13

    Default Re: steps in process

    I normally do early morning or late afternoon....that seems to work